On Trackhigh confidenceInfrastructure

Rapidly complete the Polavaram project

Telugu Desam Party · Andhra Pradesh Assembly Election 2024

Last updated 13 Jun 2026

Rapidly complete the Polavaram project.

From the Telugu Desam Party manifestoView Manifestop.7

Our Assessment

high
high

Actively progressing: the 1,372-metre diaphragm wall was completed (works begun January 2025), the project was reported around 76.79% complete, the Centre sanctioned Rs 12,157 crore, and the government set an October 2026 / pre-2027 Godavari Pushkaralu completion target. Not yet complete.